Status Reports: Separating Information from News

I am sure you have heard the old saw where it was proclaimed that dog-bites-man is not news, but man-bites-dog is news. While the news can be a source of entertainment, especially when some man bites a dog, such incidents are anecdotal at best—a statistic with a sample size of one. We should also consider that tabulated instances of dog-bites-man and related details can be statistically analyzed for correlations like breed, time of year, distance from the animal’s home, the behavior of the man immediately prior to the incident, and so on. We call this information.

That does not mean that the news has less merit than the information. It simply means that we should distinguish between the two types of content. And you should include both types of content in project status reports. Smart decision-makers stay current on the news but base their decisions on information.

Project News

Projects are like novels, described by my high school English teacher, Ray Rockwell, as “One damned thing after another.” That said, some activities are recurring or spread over a long period of time, while other activities and events are one-off or are notable as start or end points of longer duration events. This is where we separate the news items from the data points.

Project reporting periods vary, based on the projects and the needs of the stakeholders, but let us assume you are reporting each week. Some of the news items you might want to cover in your status report include:

  • Milestones achieved or missed
  • Delayed events or previously reported activities that were finally completed
  • Noteworthy achievements by team members or the team overall (kudos)
  • Noteworthy misses or failures by the team, and what was learned

I could go on, but you get the idea. These are events, both planned and unexpected, at a point in time. Timing is important, as old news is no news, and while a few news items are worth interrupting scheduled programming, most are not.

Project Information

Projects tend to generate a lot of data that can and should be tracked over time. For example, it can be helpful to understand how risk exposure has evolved over the course of a project. If the project team is continually updating the risk register and the qualitative and quantitative assessment scores, and you have an agreed way to aggregate all those risk scores, a graph of the cumulative risk exposure can show the trend. If you score open issues, that can be a second line on the chart. Add those to a line with a burndown chart of planned work and insert major milestones, and you have a picture that tells a compelling story.

During the test stages of a project, graphs can tell your stakeholders a lot about your increasing confidence in the product quality. I saw another team graph knowledge capture and transfer as a burndown chart, to the delight of the folks who would assume support responsibilities after moving to production. Think about your stakeholders and the sort of information (as opposed to news) that they will focus on. Not everyone will care about labor utilization trends or cumulative spend, but if your audience wants it, you track it. Chance favors the prepared and management favors the proactive.

Project Scorecards

For score-at-a-glance, the majority of us have adopted a Red-Amber-Green status declaration for a quick and easy summary of the detailed message. The key here is to make these broad assessments the result of an actual score, decided in advance of the project. I have written before about making these indicators rigorous, but let us be clear about their value to the consumers of your reports. They should call attention to something to be investigated elsewhere in your report. If you have one overall RAG stoplight and six detail-level stoplights, ensure your project news and information are organized in a way that lets them find the details quickly. Do not force your CFO to read the whole status report to find the sentence that says, “Consultant labor spend is running 10% ahead of plan.” Highlight the bad news!

Communication Leads to Influence

We prepare project status reports because we want to communicate with our stakeholders, make them aware of progress, roadblocks, and speed bumps. Influence them to act on the things that require their action. A good project status report does not “spook the herd,” but it does let the management know what to expect. And the key to becoming a positive influence is by managing expectations.

 

For more brilliant insights, check out Dave’s blog: The Practicing IT Project Manager

Are you involved in a data conversion project? Then check out Dave’s indispensable book: The Data Conversion Cycle

Tags
Show More
X

We use cookies on our website

We use cookies to give you the best user experience. Please confirm, if you accept our tracking cookies. You can also decline the tracking, so you can continue to visit our website without any data sent to third party services.